G Mining Ventures Provides Tocantinzinho Project Update, by @newswire
TSX: GMINOTCQX: GMINF
ceo.ca
- Project remains on schedule and on budget for commercial production in H2-2024
- Total project progress of 93% with construction 95% complete
- Total spend of $447 million (98% of project total)
- Industry leading safety record, with LTIFR of 0.04 after 5.2 million person-hours worked
- 1.5 Mt of ore at 0.85 g/t stockpiled to date ahead of schedule
- Site energized on the national grid with all balance of plant infrastructure commissioned; process plant commissioning in focus and progressing according to the plan and schedule