Vergessen darf man allerdings nicht dass Ivanhoe auch noch 2 WEITERE GROSSPROJEKTE hat.
Die noch nicht in Produktion sind.
Also von Der Seite dürfte Der Kapitalmarkt voraussichtlich noch benötigt werden, und sind Sie noch nicht "durch" mit Ihrem Finanzierungsbedarf.
Wie gesagt, Ivanhoe hat "meistens ein bisschen mehr zu erzählen"
Ivanhoe Mines issues Q2 financial results and reviewof operations, mine construction and exploration progress
- Kamoa-Kakula Copper Mine achieved Phase 1 commercial production on July 1, 2021; first phase projected to produce approximately 200,000 tonnes of copper per year
- Kamoa-Kakula’s Phase 2 expansion, scheduled for Q3 2022, will double annual copper output to approximately 400,000 tonnes
- Ivanhoe Mines pledges net-zero greenhouse gas emissions at the Kamoa-Kakula Copper Mine
- Good progress being made on Ivanhoe’s Western Foreland exploration program, searching for DRC’s next tier-one copper discovery
- Development of the world-scale Platreef palladium, rhodium, platinum, nickel, copper and gold project in South Africa MAKING EXCELLENT PROGRESS
- Kamoa-Kakula’s Phase 1 concentrator plant achieved commercial production on July 1, 2021. Kamoa-Kakula’s initial production guidance, on a 100%-project basis, is between 80,000 and 95,000 tonnes of copper in concentrate for 2021.
- Kamoa-Kakula’s Phase 2 construction is progressing slightly ahead of plan and remains on track for start-up in Q3 2022, which will see a doubling of mill throughput to 7.6 million tonnes per annum (Mtpa). Phases 1 and 2 combined are forecast to produce approximately 400,000 tonnes of copper per year.
- Study work to accelerate Phase 3 mine and concentrator expansion to at least 11.4 Mtpa is ongoing. Based on independent benchmarking, the project’s phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world’s second-largest copper mining complex, with peak annual copper production of more than 800,000 tonnes.
- At the end of July 2021, Kamoa-Kakula’s surface ore stockpiles held approximately 3.54 million tonnes grading 4.77% copper, containing more than 168,000 tonnes of copper.
- Ivanhoe, together with its partner Zijin, is exploring the acceleration of the Kamoa-Kakula Phase 3 concentrator expansion, which includes optimization work to determine mining production capacity and costs at the various mining areas on the Kamoa-Kakula complex, including expanded facilities at the Kansoko Mine, Kamoa North (including the Bonanza Zone) and Kakula West. Kamoa Copper also is refining its longer-term downstream processing strategy, including the potential construction of a smelter or hydrometallurgical processing facility.
- In April 2021, Ivanhoe Mines Energy DRC entered into an agreement with the DRC’s state-owned power company Société Nationale d'Électricité (SNEL) to upgrade a major turbine at the Inga II hydropower facility. The upgraded turbine is expected to produce 162 megawatts (MW) of clean, renewable hydropower, providing the Kamoa-Kakula Copper Mine with sufficient, sustainable electricity for future expansions, including a copper smelter.
- In May 2021, Ivanhoe pledged to achieve net-zero operational greenhouse gas emissions (Scope 1 and 2) at the industry-leading Kamoa-Kakula Copper Mine. Since the mine already is powered by clean, renewable hydro-generated electricity, the focus of the company’s net-zero commitment will be on electrifying the project’s mining fleet with new, state-of-the-art equipment powered by electric batteries or hydrogen fuel cells. Emissions-free underground mining equipment, at the size and scale required for Kamoa-Kakula’s bulk-scale operations, is at an advanced stage of development by several of the world’s leading equipment manufacturers.
- During Q2, Ivanhoe continued its 2021 copper exploration program on its Western Foreland licences that cover a combined area of approximately 2,550 square kilometres in close proximity to Kamoa-Kakula. Drilling in the quarter was focused on the western and eastern extensions of the Makoko Discovery, as well as the northern and western extensions of the Kiala Discovery. Good progress was made on construction of critical infrastructure to access high-priority, newly-acquired westerly exploration permits, including construction of a 60-kilometre spine road across the Western Foreland and a new bridge across the Lubudi River.
- In February 2021, Ivanhoe announced that its South African subsidiary, Ivanplats, is arranging project-level financing of up to $420 million to advance development of the world-scale Platreef palladium, rhodium, platinum, nickel, copper and gold project in South Africa.
- Ivanplats has signed a non-binding term sheet with Orion Mine Finance, a leading international provider of production-linked stream financing to base and precious metals mining companies, for a $300-million gold, palladium and platinum streaming facility. Ivanplats also has appointed two prominent, international commercial banks – Societe Generale and Nedbank – as mandated lead arrangers for a senior project debt facility of up to $120 million.
- Ivanplats’ proposed financings follow the November 30, 2020 issuance of the outstanding findings of an independent Platreef Integrated Development Plan 2020 (Platreef IDP20), which consists of an updated feasibility study (Platreef 2020 FS) and a preliminary economic assessment (Platreef 2020 PEA). The initial capital cost for the phased development plan under the Platreef 2020 PEA, starting at a mining rate of 700,000 tonnes per annum (700 ktpa), is estimated at $390 million.
- Detailed engineering is progressing on Platreef’s 700-ktpa initial mine design, 770-ktpa concentrator and associated infrastructure for the phased development plan, which is scheduled to be incorporated into an updated feasibility study by year end or early 2022. The Shaft 1 changeover is progressing well in preparation for permanent hoisting in early 2022. Construction activities on the Shaft 2 headframe also are advancing. In July 2021, Ivanplats ordered emissions-free, battery electric drill rigs and underground loaders from leading Swedish manufacturer Epiroc, for use in the mine’s underground development.
- Construction activities on Platreef’s Shaft 2 headframe also are advancing.
- At the Kipushi Mine redevelopment project in the DRC, the Kipushi Project’s draft feasibility study, and development and financing plan are being reviewed by Ivanhoe Mines together with its joint-venture partner and state-owned mining company, Gécamines. The project is maintaining a reduced workforce to conduct maintenance activities and pumping operations.
- Ivanhoe has made excellent progress in upgrading Kipushi’s underground infrastructure to allow for mining to quickly begin at the ultra-high-grade Big Zinc orebody. Resumption of production at the mine now requires the construction of a surface processing plant and other related production facilities. Discussions are continuing with Gécamines to advance a new era of production at Kipushi and it is anticipated that these discussions will be concluded with the finalization of the feasibility study and the agreement on the development and financing plan.
- At the end of Q2 2021, Kamoa-Kakula had reached 1.49 million work hours free of a lost-time injury, Kipushi had reached 3.44 million work hours free of a lost-time injury, and Platreef had reached 57,000 work hours free of a lost-time injury.
http://ivanhoemines.com/news/2021/ivanhoe-mines-issues-q2-financial-results-and-review-of-operations-mine-construction-and-exploration-progress/