so heute morgen kamen die news zur produktionsaufnahme
https://www.investi.com.au/api…ents/so4/a96be26d-833.pdf
Lake Way Process Plantcommissioning commences
Salt Lake Potash Limited (SO4 or the Company) is pleased to announce the commencement of Process Plant commissioningat its Lake Way Project near Wiluna, Western Australia
First time potassium rich harvest salts, precipitated from lake aquifer brine, have been fed into an SOP Plant in Australia.
•First harvest salts have beensuccessfullyfed into the feed hopper,conveyedto thesurge bin, run through thelump breaker, and theninto the attritioning feed tank at the front-end of the Process Plant.
•Over the coming weeksthe utilities, conversion circuit, flotation circuits, crystallisersand dryerwill all be commissioned ahead of full load commissioning and SOPproduction in the June quarter.
•Consultantsfrom the plant designer,Wood Group, as well as vendors Veolia and Broadbent (amongst others) will be assistingin the commissioning process.
•Front-end plantcommissioning waspowered by 2MW diesel generators. These will continue to be used to progress the commissioning activities over coming weeks.
•Gas supply lines and delivery station for the 10MW power station have beenfullycommissioned, with Power-onscheduled for late Aprilto support final commissioning activitiesand production commencement.
•First production andSOPsales on track for the June quarter.
...